At about 7:30 a.m. on Tuesday, April 5, 2016, a barge started crossing Green Lake. Hoses ran from tanker storage in a parking lot, over the walking path and out to the barge. Walkers and runners crossed the hoses on a small ramp. For six days the crew spread aluminum sulfate across the whole lake for 12 hours a day. When the work was done, according to Friends of Green Lake, the water had changed from green to blue.
When Seattle Parks and Recreation announced that treatment, it set out the terms plainly: "The alum treatment is expected to be effective for up to 10 years." This is the tenth year.
The lake's clarity depends on scheduled maintenance, and the city has already started the next round. A fourth treatment is tentatively scheduled for March 2027. The King County Council approved funding for it on October 6, and sediment sampling for it was scheduled for August 5.
Each treatment has bought a limited number of years
Alum, or aluminum sulfate, pulls phosphorus out of the water. Applied near the surface, it forms small clumps that sink. On the bottom, it covers the sediments and keeps them from releasing more phosphorus back into the lake. Algae need phosphorus, and that includes the cyanobacteria that can produce toxins. Lower the phosphorus and you limit the blooms.
Green Lake has been treated this way three times. Each treatment has a track record, and together they set the expectation for the fourth.
| Treatment | What followed |
|---|---|
| October 1991 | Phosphorus met its target for three years, though cyanobacteria levels did not appear to drop in those first three years |
| 2004 | Phosphorus and clarity goals held for 10 years, with no lake closures in the first nine. Toxic algae then closed the lake to contact recreation for two to three months in both 2013 and 2014 |
| April 2016 | Clarity, measured with a Secchi disk, went from 9 feet to 19 feet. The water's pH and dissolved oxygen did not change |
| March 2027, tentative | Planning, sampling and funding underway |
The years before 2004 show what the lake does without a fresh treatment. A 2015 Herrera analysis found that toxic algae closed Green Lake to swimming and other contact recreation in 1999, 2002 and 2003. The 2004 treatment ended that run. When its decade was up, the closures came back in 2013 and 2014. Two years later the barge came out again.
The pattern looks like a cycle. Treat the lake, get some good years, then watch the algae return. After the 1991 treatment, the first closure came in 1999. After 2004, the good stretch lasted about ten years. For the 2016 treatment, ten years was the expected life.
What year ten has looked like
King County's lake monitoring program sums up Green Lake's 2025 season in terms that read like the late stage of that cycle. On the county's Green Lake page, 2025 trophic state readings fall in the eutrophic range, meaning less clear water, high nutrient levels and more algae growth. Nitrogen-to-phosphorus ratios stayed below 25 all season. The county says that condition points to "the potential for algal blooms to be dominated by cyanobacteria." Samples from June, September and October 2025 tested above the state guideline for microcystin, a toxin cyanobacteria can produce.
In September 2025, The Seattle Times reported that Public Health – Seattle & King County had advised people and pets to stay out of Green Lake because of toxic algae, and that Seattle Parks was posting signs around the lake. Under that advisory, boating and fishing were still allowed. Anglers were told to clean their fish and throw away the guts, and everyone was told to avoid scum. King County describes the usual process on its beach page. Public Health reviews test results and recommends closing or reopening a beach to the parks department that runs it.
The clarity numbers tell the same story. After the 2016 treatment, a Secchi disk stayed visible down to 19 feet. At Friends of Green Lake's July 2026 meeting, the volunteer monitoring update called clarity "good at ~ 2 m Secchi Depth," which is roughly six and a half feet.
King County's long-term trends suggest Green Lake's water quality "has been declining over time, with increasing chlorophyll, nitrogen, and phosphorus concentrations." The county says those trends show up "even with two alum treatments (2004 and 2016)" since its monitoring program began in 2005. Each reset has worked for a while, but the lake has been getting worse under them.
The fourth treatment is already on paper
Friends of Green Lake shared the plan at its July 28, 2026 meeting. According to the meeting packet, Seattle Parks has contracted Herrera to design, oversee and monitor "the fourth alum treatment of Green Lake tentatively scheduled for March 2027." Herrera also prepared the 2015 analysis and wrote the reports on the 2016 treatment. The packet lists sediment core sampling at seven locations on August 5, 2026. It also notes that Seattle Parks "is interested in possibly updating lake closure procedures."
The packet's task table shows the project calendar:
- Treatment and monitoring plan, June 1 to December 1, 2026
- Management reserve fund, October 2026 through December 2027
- Permit-required water quality monitoring, all of 2027
- Treatment oversight, February 1 to April 30, 2027
- Public and Ecology notifications, March 1 to April 30, 2027
- Treatment report, October to December 2027
Funding came on October 6, 2026, when the King County Council passed Ordinance 2026-0238. The ordinance allocates the county's WaterWorks grants for the 2025-26-27 cycle and includes $200,000 for the City of Seattle's parks department for "Green Lake Alum Treatment."
That timing fits the lake's history. The 2016 treatment was also applied in early April. It came about two years after the 2013 and 2014 closures and about 12 years after the 2004 treatment. If the 2027 date holds, the gap since 2016 will be about 11 years, and the treatment will come after a 2025 season with three months of elevated toxin readings.
What the last one looked like from the path
The 2016 treatment gives the best preview of what spring 2027 could look like along the loop, though the 2027 plan may handle staging and closures differently.
- The staging site. Seattle Parks closed the parking lot north of the Green Lake Small Craft Center, 5900 West Green Lake Way N., for staging. The city scheduled two weeks for staging and treatment, from April 4 to April 18, 2016.
- The volume. HAB Aquatic Solutions applied 81,744 gallons of aluminum sulfate and 40,905 gallons of sodium aluminate. The sodium aluminate acts as a buffer. Both were spread evenly over the entire lake.
- The supply line. The chemicals were trucked in from as far away as Edmonton, Alberta, and kept in separate tanks in the lot near the Small Craft Center.
- The path. A ramp over the hoses kept the foot path open for the whole treatment.
- The timing of results. The city said the treatment takes effect as soon as it is applied.
By its own account, the 2016 treatment had a clear goal: "to prevent future closures of the lake to recreational uses due to toxic cyanobacteria for up to 10 years."
The rest of the park is on a 2027 clock too
The lake isn't the only part of Green Lake Park with a major reset ahead. On October 20, 2026, Seattle Parks updated its project page to say it would resume planning, design and construction for the Green Lake Community Center, Aquatic Center and Play Area. Friends of Green Lake's packet describes the project as "a historic investment of over $88.5 million." Plans call for a new community center with a full-size basketball gym and a renovated Evans Pool building with a six-lane, 25-yard lap pool. A warm-water pool would be added if funding allows. A July 2026 project presentation puts the construction start in late 2027, with building continuing through 2028 and 2029.
For now, the current buildings are running on their posted fall 2026 schedules. The community center is open weekdays from 10 a.m. to 9 p.m. and Saturdays from 8:30 a.m. to 5 p.m., and it is closed Sundays. Evans Pool's fall session runs through December 20.
The Pathway of Lights is on December 12, 2026. The Green Lake Community Center has run this free event for more than 40 years, with support from Seattle Parks and Recreation, volunteers and local businesses around the lake. It is the park's last big night on the current campus calendar before the treatment barge and the construction crews arrive.
People who follow how Green Lake's park projects and lake work fit into the rhythm of the neighborhood often ask how that affects the homes around it. If that question is on your mind this winter, Dorothee Graham is glad to talk it through over coffee near the lake, with no agenda beyond a good conversation. Let's Connect.